1Substrate inspection and preparation standard
Preparation standard:Substrate firm, level and free of standing water
Roughness requirement:per product requirements
Cleanliness requirement:free of oil/grease and dust
Crack repair:Cracks over 0.5 mm: apply a "one fabric, three coats" reinforcement treatment
Internal/external corner treatment:Form internal/external corners into arcs and reinforce pipe roots with sealant
2Paint preparation and mixing
Must be used up within the specified pot life after mixing.
Mixing method:Stir until uniform (mix two components at the label ratio).
3Environmental condition check
Application temperature:5-35°C
Relative humidity:relative humidity ≤85%