Epoxy Terrazzo Flooring | KF-ET500 | Kexin New Materials

Epoxy floor coating series · complete application process flow

Product No.: KF-ET500 Reference standards: GB/T 22374 | JC/T 1015 | ASTM D7234 Version: V2.0 Date: 2026-06-21
I. Pre-application preparation — Substrate inspection and treatment

1Substrate inspection and preparation standard

Preparation standard:Concrete substrate grinding / shot blasting

Roughness requirement:CSP 3-5 (ICRI standard)

Cleanliness requirement:Free of oil, laitance and loose particles

Moisture content:Moisture content <6% (CM method)

pH value:pH<10

Crack repair:Cracks >0.5 mm require V-grooving and repair with epoxy mortar

2Paint preparation and mixing

Mixing method:Mix with electric stirrer at 300-500 rpm for 3-5 minutes

Mixing ratio:Mixing ratio as indicated on the product label

Curing:Two-component: induction time 10-15 minutes

Pot life:Pot life after mixing approx. 30-60 minutes (23°C), varies by product

3Environmental condition check

Application temperature:10-30°C (substrate temperature at least 3°C above the dew point)

Relative humidity:relative humidity ≤85%

Ventilation requirements:Good ventilation

II. Application procedure — Selection of coating method
Application methodProcess parametersApplicable scenarios
Trowel / screed application (self-levelling) notched trowel, control spreading rate Large-area flooring
Roller application (thin-film type) Medium-nap roller Thin-film flooring / topcoat
Spray coating Airless spray Orange-peel / anti-slip flooring
III. Recoat Interval and Curing

Minimum overcoating interval:Can be overcoated when touch-dry (approx. 8-12 hours at 23°C)

Maximum overcoating interval:Beyond 48 hours, sanding and roughening required

⚠ Risk of intercoat adhesion failure when overcoating after the maximum recoat interval:When the maximum overcoating interval is exceeded, intercoat adhesion will drop significantly; the surface must be sweep-blasted (low pressure 0.2-0.3 MPa, non-metallic abrasive) to create mechanical anchor roughness, otherwise the coating will delaminate.

Curing conditions:At 23°C: foot traffic after 24 hours, light service after 72 hours, fully cured in 7 days. Avoid contact with water during curing.

4. Safety and environmental requirements
⚠ PPE requirements: respirator + goggles + rubber gloves + safety shoes
⚠ Ensure good ventilation of the work area to prevent solvent build-up
⚠ Open flames strictly prohibited during curing
⚠ Waste paint disposed of as hazardous waste
5. Quality inspection and acceptance criteria
Inspection itemsInspection methodAcceptance criteria
Substrate moisture content CM method / hygrometer <6%
Dry film thickness Coating thickness gauge Complies with design values
Adhesion Pull-off method ≥2MPa
Flatness 2 m straightedge ≤2mm/2m
Hardness Pencil hardness ≥2H
Prepared on the basis of:GB/T 22374 | JC/T 1015 | ASTM D7234 and the relevant industry standards.
Important statement:This application guide is a recommended guidance document; actual application parameters should be adjusted according to site conditions, environmental status and coating system requirements. For special working conditions or difficult application problems, please contact the Kexin New Materials technical department for professional support.